Project started October 2023,

 
 
 
We clamped a piece of steel to the frame exactly straight and used that as a base for the magnetic drill. Then Aad welded the first plug in and we bolted the steel plate to that to drill the hole for the second plug. All this will result in an almost invisible rubbermount. Aad also welded some halfrond bar to the top to create a rib.
 
 
 
 
Where the sides and bottom join we also added some roundbar, and we made a little tool to help weld the sheetmetal in the center of the bar, sometimes the simplest tool can make a big difference!

 
 
 

Almost ready, only need to weld the top and bottom together and clean up all the welds now. After that we start on some new handlebars.